Hobsonville Point wastewater pump station

  • Hobsonville Point, The Airfields
  • In Progress
  • Development

Hobsonville Point needs another wastewater pump station so that this thriving community can continue to grow.

This new pump station will futureproof Hobsonville Point so that capacity isn’t an issue.

About the project

More homes are planned for the growing and thriving neighbourhood of Hobsonville Point, but forecasts indicate that the capacity of the existing wastewater pump station in the area is not sufficient for the projected development in the area. Therefore, a new wastewater pump station known as pump station 6 (PS6) is required, to ensure existing and future residents can continue to rely on safe, reliable wastewater services.

Where will the pump station be?

The new pump station will sit on the edge of a reserve at the intersection of Bomb Point Drive and Glidepath Road. It will be fenced-off and landscaped, minimising visual impact. A rising main will be installed to connect to the existing Watercare wastewater manhole at the intersection of Hobsonville Point Road and Corsair Street.

An existing wastewater pump station on Bomb Point Drive gives an indication of what the site will look like when completed with fencing and landscaping.

An indicative image of the wastewater pump station site, noting that the large storage tank (red rectangle) will be underground.

When will the work happen?

The work will happen in overlapping stages between June 2024 and February 2025:  

  • Stage 1 (July to September 2024): Installing a rising main which takes wastewater along Glidepath Road and then Hobsonville Point Road, to the existing Watercare wastewater manhole at the intersection of Hobsonville Point Road and Corsair Street.  
  • Stage 2 (August to October 2024): Installing an emergency storage tank and emergency overflow pipe from the pump station to Catalina Bay. 
  • Stage 3 (September to December 2024): Installation of a gravity main pipe along Bomb Point Drive that directs wastewater into the pump station. 
  • Stage 4 (mid-2024 to early 2025): Construction of the pump station at the intersection of Bomb Point Drive and Glidepath Road.

We are working hard to ensure any disruption is minimised while work is underway, although some disruption, such as sections of roads being closed, should be expected. 

We will communicate and engage directly with affected residents and businesses as work progresses.

 

Why is Eke Panuku building the new pump station?

Watercare is usually responsible for Auckland’s wastewater infrastructure. However, there is an agreement in place between Eke Panuku (on behalf of Auckland Council) and Kāinga Ora – Homes and Communities to ensure the land in Hobsonville Point is ready for development. This is based on a legacy infrastructure funding agreement between Waitākere City Council and the Hobsonville Land Company (later renamed Homes Land Community Ltd., and now part of Kāinga Ora).

On behalf of Auckland Council, Eke Panuku is leading the procurement, design and overseeing the delivery of the project. CB Civil is the contractor.

This page will be updated as the project progresses.

Updates:

19 July 2024

Lane closure on Hobsonville Point Road for one week.

From Monday 22 July until Friday 27 July (inclusive), one lane will be closed on Hobsonville Point Road from De Havilland Road to Corsair Street, as we continue to locate underground utility services in this area.

We will work as quickly as possible to minimise disruption. Traffic management remains in place to keep road users and pedestrians safe.

 

17 July 2024

Lane closure on Hobsonville Point Road as potholing progresses.

From Wednesday 17 July, for the rest of the week (the remainder of the school holidays), we will be closing one lane on Hobsonville Point Road from De Havilland Road (near Hobsonville Point Primary School) to Glidepath Road, to locate underground utility services in this area. 

Traffic management remains in place to keep road users and pedestrians safe.

 

5 July 2024

Traffic management in place while potholing progresses.

Starting from Monday 8 July, we will continue with locating underground utility services along Glidepath Road to Hobsonville Point Road, and then to Corsair Street. These potholes will be temporarily backfilled until permanent reinstatement towards the end of the project.

We anticipate this stage to take around seven weeks total, with work happening between the hours of 7am - 5.30pm Monday to Friday. Sections of the road will be closed as we work, but we aim to keep one lane open at all times. Street parking will be unavailable, and any disruption to driveway access will be kept to a minimum.

 

27 June 2024

Temporary closure of Bomb Point Drive (Glidepath Road to Commanders Avenue)

The first step of the Pump Station 6 project requires identifying the location of underground utility services (like stormwater and water pipes and power lines), to help lock in the pathway for the rising main.

We do this by making several small excavation potholes to find the services. This work will start on Thursday 27 June along Bomb Point Drive between Glidepath Road and Commanders Avenue.

As a result, the road will be closed temporarily as we work in this area. We anticipate this will last about a week, with a road detour in place. The road will be open on the weekends, including the Matariki public holiday on Friday 28 June.  

Footpaths will remain open throughout. 

Camera Four Outdoor Entry Bridge Max
  • Northcote
  • In Progress

Northcote's greenway Te Ara Awataha

15/11/2017 - 31/12/2027

Find out more
Westhaven Karakia 122023 7267
  • Westhaven
  • Stage 2 complete

Berth and public access improvements

03/04/2023 - 05/12/2023

Find out more
WQ Ferry 052024 1106
  • Wynyard Quarter
  • In Progress

Free Wynyard Quarter 'Red Boats' ferry

11/05/2024

Find out more